Getting a new electricity connection is one of the most important steps after purchasing or constructing a house. Residents of Engineers Town must follow specific guidelines and submit certain documents before the connection can be approved and installed.

This guide explains the documents required, inspection process, installation requirements, and important conditions for obtaining a new electricity connection.

1. Required Documents for Electricity Connection

To apply for a new electricity connection, the applicant must submit the following documents to the Sub-Divisional Officer (SDO) Operations office.

Documents Required

  • Proof of property ownership (such as allotment letter or registry).

  • Attested copy of the applicant’s CNIC.

  • Power of Attorney (if the application is submitted by a representative).

  • No Objection Certificate (NOC) from the relevant authority if required.

  • Formal application/request letter for the electricity connection.

  • Property map/site plan prepared on a scale of 1 inch = 100 feet.

  • Two passport-size photographs of the applicant.


Make sure that all documents are complete and properly attested before submission to avoid delays.




2. Inspection Process

Once the application is submitted with all required documents, the electricity company will conduct a site inspection within three days.

During this inspection, officials verify:

  • The location of the property

  • The proposed meter installation point

  • Safety requirements

  • Electrical load requirements

After successful verification, the process for connection installation begins.

3. Electricity Load and Cable Requirements

In the area, single-phase electricity supply is generally available.

The system supports:

  • Maximum load: 4 kW + 10% tolerance

Applicants must install the required electrical infrastructure according to company standards.

Wiring Requirements

  • A 16 mm² service cable must be installed.

  • The cable should run from the meter location to the main distribution board inside the house.

  • All internal wiring must comply with approved electrical safety standards.

Proper wiring ensures safe and reliable electricity supply.

4. Location of Service Connection

The electricity service connection will be installed on the boundary wall of the property.

This location allows easy access for:

  • Meter reading

  • Maintenance

  • Safety inspections

Residents should make sure the boundary wall is ready before installation.

5. Meter Board Preparation

Before the electricity connection is installed, the applicant must prepare the meter board according to company specifications.

The meter board should:

  • Be securely installed

  • Follow approved size and safety standards

  • Be easily accessible for utility staff

Failure to prepare the meter board properly may delay the installation process.

6. Important Compliance Rules

Residents must follow all electricity rules and regulations after the connection is installed.

The electricity company reserves the right to disconnect the connection without prior notice if any rules are violated.

Examples of violations include:

  • Unauthorized load increase

  • Illegal wiring

  • Safety hazards

  • Tampering with the meter

Final Advice for Residents

To ensure a smooth electricity connection process:

  • Prepare all required documents beforehand.

  • Install proper wiring and service cables.

  • Follow company safety standards.

  • Cooperate during inspection.

By following these steps, residents of Engineers Town can obtain their electricity connection quickly and without complications.